RTUEE / EC / EEEYr 2021 · Sem 72021

Q8Power System Planning

Question

16 marks

Q.4. (a) Explain the Reactive Compensation. What are the reasons that shunt capacitors are employed at substation level? [8]

(b) Explain computer aided process also write its classification and its advantages over manual experience based process planning. [8]

Answer

(a) Reactive Power Compensation and Shunt Capacitors at Substation Level

Reactive power compensation refers to deliberately supplying or absorbing reactive power (VAR) at specific points of the network using devices such as shunt capacitors, shunt reactors, synchronous condensers or static VAR compensators, so that the reactive power balance of the system is maintained close to the load point rather than being transported over long distances from generators. Most loads (induction motors, transformers, fluorescent/discharge lighting) are inductive in nature and draw lagging reactive power in addition to active power; if this reactive demand is met entirely from generators located far away, it must flow through the transmission and distribution network, causing additional current, losses and voltage drop for no useful active-power transfer.

  • Reduce reactive power flow through transmission and distribution lines, thereby reducing the total current and hence the I-squared-R (copper) losses in conductors and transformers.
  • Improve the voltage profile at and downstream of the substation, since supplying reactive power locally reduces the voltage drop that would otherwise occur across line/transformer impedance when reactive power is drawn from a remote source.
  • Release transmission and transformer capacity, because reducing the reactive component of current frees up thermal capacity of the same equipment to carry additional active power, effectively increasing the usable capacity of existing assets without new construction.
  • Improve the power factor at the substation/consumer interface, which is often directly incentivized (or penalized if poor) through utility tariff structures with power-factor surcharge/rebate clauses.
  • Reduce the kVA demand registered for billing purposes, since apparent power (kVA) is reduced when the reactive component is compensated locally, lowering demand charges for industrial/commercial consumers with kVA-based tariffs.

Shunt capacitors are preferred at the substation level because they are relatively low cost, have no rotating parts (low maintenance), can be switched in discrete steps (banks) to follow the varying reactive demand of the connected load, and are simple to install at existing substations without major civil work, making them the most widely used means of reactive compensation in distribution and sub-transmission networks.

(b) Computer Aided Process Planning (CAPP) - Classification and Advantages

Computer Aided Process Planning (CAPP) is the application of computer software to assist in, or automatically generate, the sequence of operations and associated parameters required to produce or plan a product/process, replacing or supporting the traditionally manual, experience-based process planning function. In the context of power system/engineering planning, CAPP-type systems are used to standardize and speed up repetitive planning/design tasks by drawing on stored knowledge of similar previously solved cases or by applying codified planning rules.

  • Variant (retrieval-based) CAPP: relies on group technology, in which components/situations are classified and coded according to similarity of features; when a new case arises, the system retrieves the process plan of the most similar existing case from a database and the planner edits it to suit the specific requirement. This approach is simpler to implement but is limited to the range of cases already stored.
  • Generative CAPP: uses a codified set of design/manufacturing rules and decision logic (often an expert-system approach) to automatically generate a new process plan from scratch for any new case presented, without needing a directly similar stored precedent, and is therefore more flexible but more complex to develop and validate.
  • Consistency: computer-generated plans apply the same logic/rules every time, eliminating the variability that arises when different experienced planners solve the same problem differently.
  • Speed: automated retrieval or generation of a plan is far faster than manual derivation from first principles by an experienced engineer.
  • Reduced dependency on scarce experienced personnel: codified rules/database capture institutional knowledge, reducing the risk and cost associated with loss of experienced staff.
  • Easier updating of standards: when a standard, code or best practice changes, the rule base/database can be updated centrally and immediately applies to all future plans, rather than relying on individual planners to remember the change.
  • Improved auditability and traceability: automated systems maintain a clear, repeatable record of how a particular plan was derived, aiding quality assurance and regulatory review.

Sizing and location of shunt capacitor banks is itself a planning optimization problem: capacitors placed too close to the source provide little loss reduction benefit, while capacitors placed too far downstream near light loads can cause overvoltage during low-load periods; utilities therefore use power-flow-based capacitor placement studies, often supported by switched (rather than fixed) capacitor banks with automatic voltage or power-factor-based control, to ensure the reactive compensation tracks the actual variation of load through the day and across seasons.

The choice between variant and generative CAPP approaches in practice often depends on the maturity and standardization of the underlying planning task: highly standardized, repetitive tasks with a large historical case base (such as routine distribution transformer sizing) are well suited to variant, retrieval-based systems, whereas more novel or highly variable planning tasks benefit from a generative, rule-based approach that does not depend on the availability of a closely matching precedent, though generative systems require significantly greater upfront investment in codifying the underlying engineering rules correctly.

Reactive power planning at the system level is closely coordinated with active power (generation expansion) planning, since inadequate reactive support in a heavily loaded network can itself become the binding constraint on how much active power can be transmitted before voltage collapse risk becomes unacceptable; utilities therefore run dedicated reactive-power/voltage-stability planning studies alongside conventional thermal-loading studies when evaluating the adequacy of a proposed transmission expansion.

The economic benefit of shunt-capacitor reactive compensation is generally evaluated using a simple payback or net-present-value comparison between the capital cost of the capacitor bank and switching equipment against the discounted value of the loss reduction, voltage-improvement and capacity-release benefits it provides over its service life, and utilities typically find that capacitor compensation offers one of the most cost-effective loss-reduction measures available at the distribution level compared with alternatives such as conductor upgrading.

CAPP-type systems in a broader engineering-planning context are also increasingly integrated with computer-aided design (CAD) and geographic information system (GIS) platforms, so that a generated process or network plan can be directly visualized and further refined on the same digital platform used for detailed engineering drawing and asset mapping, reducing data duplication and transcription errors between the planning stage and the subsequent detailed design and construction stages.

Back to Paper